[1]聂文波,李凤义,陈雷.桃山三井胶结充填管输系统试验研究[J].西安科技大学学报,2014,(05):523-527.[doi:10.13800/j.cnki.xakjdxxb.2014.0503]
 NIE Wen-bo,LI Feng-yi,CHEN Lei.Research on coarse fly ash filling slurry pipeline system for Taoshan mine[J].Journal of Xi'an University of Science and Technology,2014,(05):523-527.[doi:10.13800/j.cnki.xakjdxxb.2014.0503]
点击复制

桃山三井胶结充填管输系统试验研究(/HTML)
分享到:

西安科技大学学报[ISSN:1672-9315/CN:61-1434/N]

卷:
期数:
2014年05期
页码:
523-527
栏目:
出版日期:
2014-10-31

文章信息/Info

Title:
Research on coarse fly ash filling slurry pipeline system for Taoshan mine
作者:
聂文波1李凤义2陈雷1
1.黑龙江科技大学 安全工程学院,黑龙江 哈尔滨 150022; 2.黑龙江科技大学 矿业研究院,黑龙江 哈尔滨 150022
Author(s):
NIE Wen-bo1LI Feng-yi2CHEN Lei1
1.Safety Engineering Institute,Heilongjiang University of Science and Technology,Harbin 150022,China; 2.Mining Research Institute,Heilongjiang University of Science and Technology,Harbin 150022,China
关键词:
充填开采 流体力学 管道输送 全程管压
Keywords:
filling mining fluid dynamics pipeline the entire pressure pipeline
分类号:
TD 823.7
DOI:
10.13800/j.cnki.xakjdxxb.2014.0503
文献标志码:
A
摘要:
为了解决桃山三井工作面充填开采过程中出现的堵管以及管道的高磨损率等问题,运用流体力学和采煤学,结合该工作面的实际情况,采用自流+泵送的管道输送技术进行了工业试验,并利用ANSYS模拟分析了在工业既定速度2.0 m/s时不同料浆浓度、管径对全程管压的影响。模拟结果表明:在既定输送速度下,管压在合理的可控范围内且易于输送时的充填料浆浓度、管径取值范围分别为52%,140~180 mm时,此时的输送管压分别为134.561 kPa,130.053~138.759 kPa; 利用模拟结果进行料浆输送的工业试验结果表明,堵管、管道磨损得到了解决,充填开采取得良好的效果,有效地控制了顶底板的变形,降低了顶板的下沉量,减少对环境的破坏,同时也表明该管输系统是一种“安全、经济、环保、可靠”的充填采煤系统,为该矿以及类似条件下的矿山充填开采提供了借鉴作用。
Abstract:
In order to solve the mitsui peach mountain face appeared in the process of filling wall pipe and high wear rate of the pipeline,an introduction to using the fluid mechanics and mining,in combination with the practical situation of the working face,using their+pump pipeline technology,the industrial experiment and ANSYS simulation analysis in the industry established speed 2.0 m/s different slurry concentration,the influence of the diameter for the entire pipe pressure.Simulation results show that under the given delivery speed,pipe pressure within the reasonable control and easy to transport the filling slurry concentration,pipe diameter value range of the 52%,140 to 180 mm respectively,at this time of pipeline pressure were 134.561 kPa,130.053~138.759 kPa; Slurry transportation industrial test is carried out using the simulation results show that the blocking pipe,pipe wear has been resolved,and filling to obtain good effect,effectively control the deformation of roof and floor,reduces the roof subsidence,reduce the damage to the environment,also show that the pipeline system is a kind of “safety,economy,environmental protection,reliable” filling mining system,for the mine and similar mine under the condition of filling mining provides reference.

参考文献/References:

[1] 钱鸣高,许家林,缪协兴.煤矿绿色开采技术[J].中国矿业大学学报,2003,32(4):343-348. QIAN Ming-gao,XU Jia-lin,MIAO Xie-xing.Green technique in coal mining[J].Journal of China University of Mining and Technology,2003,32(4):343-348.
[2] 王新民,肖卫国,张钦礼.深井矿山充填理论与技术[M].长沙:中南大学出版社,2005. WANG Xin-min,XIAO Wei-guo,ZHANG Qin-li.Deep well mining filling theory and technology[M].Changsha:Central South University Press,2005.
[3] 郑晶晶,张钦礼,王新民.充填管道系统失效模式与影响分析(FMEA)及失效影响模糊评估[J].中国安全科学学报,2009,19(6):166-171. ZHENG Jing-jing,ZHANG Qin-li,WANG Xin-min.FMEA analysis of backfilling pipeline system and fuzzy evaluation of failure effects[J].China Safety Science Journal,2009,19(19):166-171.
[4] 李少辉.粉煤灰的特性及其资源化综合利用[J].混凝土,2010,25(4):45-47. LI shao-hui.Characteristics and comprehensive resour-ces utilization of fly ash[J].Concrete,2010,25(4):45-47.
[5] 金子桥,吕宪俊,胡术刚,等.膏体充填料浆水力坡度研究进展[J].金属矿山,2009,401(11):35-37. JIN Zi-qiao,LV Xian-jun,HU Shu-gang,et al.Development of research on hydraulic gradient of paste backfill slurry[J].Metal Mine,2010,25(4):45-47.
[6] 李永业,孙西欢,阎庆绂,等.不同导流条安放角条件下筒装料管道水力输送试验研究[J].水动力学研究与进展(A辑),2008,23(1):86-89. LI Yong-ye,SUN Xi-huan,YAN Qing-fu,et al.Experimental research on the piped hydraulic transportation with the different diversion angle[J].Journal of Hydrodynamics(Ser.A),2008,23(1):86-89.
[7] 李 翔,王金安,张少杰.复杂地质体三维数值建模方法研究[J].西安科技大学学报,2012,32(6):666-680. LI Xiang,WANG Jin-an,ZHANG Shao-jie.3D modeling method of complicated geological body[J].Journal of Xi'an University of Science and Technology,2012,32(6):666-680.
[8] 贾建华,张艮龙.巷道三维显示自动建模新方法[J].西安科技大学学报,2010,30(6):716-719. JIA Jian-hua,ZHANG Gen-long.3D visualization of roadway based on ArcGIS[J].Journal of Xi'an University of Science and Technology,2010,30(6):716-719.
[9] 胡红军.ANSYS10.0 材料工程有限元分析实例教程[M].北京:电子工业出版社,2008. HU Hong-jun.Tutorial ANSYS10.0 materials engineering finite element analysis of an example[M].Beijing:Electricity to the Industry Press,2008.
[10]谢龙汉.ANSYS FLOTRAN流体及热分析[M].北京:电予工业出版社,2012. XIE Long-han.ANSYS FLOTRAN fluid and thermal analysis[M].Beijing:Electricity to the Industry Press,2012.
[11]李凤义,王伟渊.新安煤矿井下沿空留巷巷旁充填实验[J].黑龙江科技大学学报,2013,23(5):409-412. LI Feng-yi,WANG Wei-yuan.Filling test filled in gob-side entry retaining in Xin'an coal mine[J].Journal of Heilongjiang Institute of Science & Technology,2013,23(5):409-412.
[12]陈维新,关显华.粉煤灰基胶结充填采煤技术及应用[J].煤矿现代化,2014,120(3):15-18. CHEN Wei-xin,GUAN Xian-hua.Fly ash based cemented filling mining technique and application[J].Coal Mine Modernization,2014,120(3):15-18.
[13]刘永兵,陈纪忠,阳永荣.管道内液固浆液输送的数值模拟[J].浙江大学学报:工学版,2006,40(5):858-863. LIU Yong-bing,CHEN Ji-zhong,YANG Yong-rong.Numerical simulation of liquid-solid two-phase flow in slurry pipeline transportation[J].Journal of Zhejiang University:Engineering Science,2006,40(5):858-863.

相似文献/References:

[1]杨宝贵,杨捷,王玉凯,等.充填开采上覆岩层移动变形研究[J].西安科技大学学报,2015,(06):732.[doi:10.13800/j.cnki.xakjdxxb.2015.0610]
 YANG Bao-gui,YANG Jie,WANG Yu-kai,et al.Research on filling mining overburden movement deformation[J].Journal of Xi'an University of Science and Technology,2015,(05):732.[doi:10.13800/j.cnki.xakjdxxb.2015.0610]